Case StudiesWest Basin - Capacity Assessment
Transform · Case Study
Capacity Simulation That Deferred ₹525 Crore of Immediate Capex
Private Seaport in India·Gujarat, India
Strategy & PlanningMarket & CustomersBusiness ExcellenceIT & Automation
Key Impact
“Business model simulation helps defer Rs. 525 Cr capex”

Context & Background
The seaport is part of a large business conglomerate in India. The port had grown substantially from its humble beginning and became the largest commercial cargo port in India. The organization had integrated mechanized coal handling facility which needed capex spend for augmenting the capacity and minimize operational delays.
Work Executed
Created model for cargo scenario
Accurately computed operational parameters for multiple complex situations
Assessed the requisite infrastructure and facilities
Worked out financial implications of different scenarios
Value Delivered
The model correctly portrayed the actual results. The exercise provided deeper insights into the port’s operating parameters and how they affected the financial obligations. Using the results from the exercise, the organization could bring down the immediate capex requirement from Rs. 700 Cr to Rs. 175 Cr only.
Key Assignment Components
#operations#efficiency#analysis#forecast#feasibility#cargo storage#conveyor#cranes#cycle time#delays
Includes work undertaken by team members as part of assignments / employment.
Facing a similar challenge?